Project Background :


The project involves the rehabilitation of a Southern Corridor section (connecting the port of Djibouti with Ethiopia) as far as the crossroads of Ali Sabieh and Dikhil roads in a total length of 10.2 km.

The work mainly concerns:

  • earthworks and pavements;
  • drainage structures: scuppers, culverts, triangular ditches;
  • bituminous concrete paving works;
  • finishing work and connections to what is in extant; and
  • safety devices (beacons, guardrails) and horizontal and vertical signs